You are managing a portfolio in a functional organization and resources are shared between operations...

You are managing a portfolio in a functional organization and resources are shared between operations and projects. You are continuously performing capability and capacity analysis in order to optimize the portfolio. Which of the following capability and capacity analysis is used to limit the number OR size of components the organization can execute?

A.

Knowledge Basis

B.

Financial

C.

Human Resources

D.

Assets