You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs...

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. For this you maintain a risk register. The risk register is used throughout the portfolio life cycle in order to track and manage risks. It is continually updated throughout the portfolio life cycle. As a portfolio manager, you know that the risk register includes all of the following except

A.

Probability Impact Assessment

B.

List of potential responses

C.

Updated risk categories

D.

Person who Identified the risk

PfMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PfMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"