Assume you work in a weak matrix structure in your pharmaceutical company in which most...

Assume you work in a weak matrix structure in your pharmaceutical company in which most of the program and project managers are coordinators, and most of the staff that supports them are in functional organizations. On some high priority programs, staff may be dedicated to the program full time for a short time period; however, operational work often takes precedence especially in manufacturing. The demand for some of the pharmaceutical products often outpaces the available supply, and shelf life is short. These fluctuations of resources then:

A.

Require use of resource smoothing

B.

Led to the development of resource heuristics as to how best to manage the portfolio

C.

Require sign-offs from functional managers on the portfolio charter concerning resource availability

D.

Impact the availability of the work managed within the portfolio

PfMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PfMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"