An Assignment uses the following Service-Level Agreement: Initial Urgency: 5, Goal: 12 hours (increase Urgency...

An Assignment uses the following Service-Level Agreement: Initial Urgency: 5, Goal: 12 hours (increase Urgency by 10), Deadline: 24 hours (increase Urgency by 15), Passed Deadline: 4 hours (increase Urgency by 20, limit to 5 events). What is the Assignment Urgency 36 hours after the Case reaches the Assignment?

A.

70

B.

90

C.

50

D.

85