You are a Product Owner.

You are a Product Owner. The Developers are close to the end of a Sprint and ask you for 3 extra days to complete their work. They feel that if they do not get the extra time, they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do? (choose the best answer)

A.

Cut back on testing, or leave some items incomplete, so long as the Developers can "substantially meet" their goal.

B.

Agree to extend the Sprint but ask the team to be more realistic when they plan Sprints in the future.

C.

Ask the Developers to work longer hours to meet their goal.

D.

Ask the Developers to commit to what was agreed and find a solution for the problem.

E.

Do not extend the Sprint and stick to the original timebox. Work with the stakeholders to explain why transparency and openness are important.

PAL-I PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PAL-I pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"