In the ADM, what is the name for documents that are not finished and not approved?
A.
interim
B.
draft
C.
version 0.1
D.
incomplete
The Answer Is:
B
This question includes an explanation.
Explanation:
In TOGAF, draft deliverables are those that are not yet finished or approved. They are work-in-progress versions that may have version numbers like 0.1, 0.5, or 0.9.
Once reviewed and approved, they become final deliverables.
[Reference: TOGAF® Standard, Version 9.2, Deliverables, Artifacts, and Building Blocks., , ]