A licensed professional working for a large engineering company is responsible for evaluating contractor bids...

A licensed professional working for a large engineering company is responsible for evaluating contractor bids for new design projects. During the bid review process for an electrical switch system, the professional realizes that one of the more promising bids has been submitted by their in-law's company.

Which of the following initial actions by the professional best fulfills their duties to the public, their employer, and themselves?

A.

Step down from the bid evaluation process to prevent bias.

B.

Ask their in-law's company to withdraw their bid, citing conflict of interest.

C.

Follow a neutral bid evaluation process and submit a detailed, final report for approval.

D.

Fully disclose to their supervisor the bidder's family relationship and then proceed under their direction.

NPPE PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now NPPE pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"