Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

Over the period of 2 to 3 weeks, a cluster displays the following:•Periods where Warning...

Over the period of 2 to 3 weeks, a cluster displays the following:

•Periods where Warning Alerts of memory usage over 75% are asserted

•Periods where Critical Warnings of memory usage over 90% are asserted

•Periods of slow of frozen VDI desktops have caused work stoppage or slowdown

•VDI clones have periodically not powered up when called, causing work stoppage

Which steps should be used to prioritize the administrator’s troubleshooting efforts?

A.

•Assess resource health on Hardware page

•Review the Analysis page for memory usage demand

•Determine the VDI workload-to-host affinity across the cluster

B.

•Analyze Alert Pages for a root cause of memory problem

•Analyze VM table page to access the VM functionality

•Analyze the VDI Clone properties for possible VDI Workload stress

C.

•Check Analysis page for CPU demand

•Verify VDI workload property for memory subscription

•Review the Hardware page to determine if the cluster has sufficient RAM

D.

•Review Analysis Page for memory use pattern

•Alert with VDI workload demand

•Analyze current and future workload in the Capacity Runaway tab for sufficient resources

NCS-Core PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now NCS-Core pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"