Developer VDI users are complaining about performance issues and states that tasks are taking longer...

Developer VDI users are complaining about performance issues and states that tasks are taking longer to complete than before. An administrator is analyzing the environment trying to determine the cause. The administrator has determined these metric values for the host:

CPU Usage = 18%

CPU Ready = 6.5%

IOPS = 250

Storage Usage = 20%

Which performance counter could explain the issue?

A.

CPU Usage

B.

Storage Usage

C.

IOPS

D.

CPU Ready