An organization is running a Nutanix Cluster based on AOS 5.

An organization is running a Nutanix Cluster based on AOS 5.10.x and VMware vSphere 6.7. Currently, the CVM network is segmented and Storage only nodes not present.

A new security project based on NSX is coming. VMware Distributed Virtual Switches are required. The administrator needs to prepare the environment for the new project.

Which step should the administrator use to initiate the project?

A.

Enable Nutanix Flow at the Prism Central Level

B.

Manually disable CVM network Segmentation

C.

Convert storage only nodes into vSphere nodes

D.

Enable Jumbo Frames to accommodate network frames

NCM-MCI-5.15 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now NCM-MCI-5.15 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"