Which of the following would MOST likely be used to review previous upgrades to a system?
A.
Business continuity plan
B.
Change management
C.
System life cycle
D.
Standard operating procedures
The Answer Is:
B
This question includes an explanation.
Explanation:
Change management is the process of reviewing previous upgrades to a system. It is a systematic approach to managing changes to an organization's IT systems and infrastructure. Change management involves the assessment of potential risks associated with a change, as well as the identification of any necessary resources required to implement the change. References: Network+ Certification Study Guide, Chapter 8: Network Troubleshooting