An IT integration delivery team begins a project by gathering all of the requirements, and...

An IT integration delivery team begins a project by gathering all of the requirements, and proceeds to execute the remaining project activities as sequential, non-repeating phases.

Which IT project delivery methodology is this team following?

A.

Kanban

B.

Scrum

C.

Waterfall

D.

Agile