The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering...

The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering ahead of schedule. This means that fewer resources are required to complete the project. The Training Project, which was due to start in Tranche 3, has now become a higher priority and needs to be started early. The programme manager has recommended starting the Training Project now although Tranche 2 and Tranche 3 will then overlap.

Is this an appropriate application of the structure' theme, and why?

A.

Yes, because available resource capacity should be fully utilized throughout the programme

B.

Yes, because tranches may overlap if the programme is making good progress and capability is available

C.

No, because tranches should be sequential to enable end-of-tranche reviews to take place before the next tranche is approved

D.

No, because tranches should remain sequential if overlapping the tranches would increase the risks to programme delivery

MSP-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now MSP-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"