The SRO is accountable for confirming Programme Mandate.
B.
The SRO is accountable for the Programme Brief.
C.
The Programme Manager is responsible for the Vision Statement.
D.
The Programme Manager is responsible for the Blueprint.
The Answer Is:
A
This question includes an explanation.
Explanation:
The Sponsoring Group, not the SRO, is accountable for confirming the Programme Mandate. The MSP Practitioner clearly states:"The Sponsoring Group is accountable for confirming the mandate,"which means the SRO oversees delivery but does not hold responsibility for initial mandate confirmation. Meanwhile, the Programme Manager has ownership of the Vision Statement and Blueprint, aligning with delivery responsibilities.