In which MSP theme would you expect to find the POTI model?
A.
Vision
B.
Blueprint Design and Delivery
C.
Leadership and Stakeholder Engagement
D.
Planning and Control
The Answer Is:
B
This question includes an explanation.
Explanation:
The POTI (Projects, Operations, Teams, and Infrastructure) model is used to define the high-level scope of the Blueprint. The Blueprint theme encompasses the detailed design and delivery aspects of the programme’s transformation. As per MSP Practitioner,"POTI defines high level scope of blueprint,"situating the model firmly within the Blueprint Design and Delivery governance theme.