Which of the following is an activity in Defining a Programme?
A.
Design the Projects Dossier
B.
Manage transition
C.
Produce the Programme Brief
D.
Align the projects with benefits realization
The Answer Is:
A
This question includes an explanation.
Explanation:
Designing the Projects Dossier is a key activity in the 'Defining a Programme' process. The Projects Dossier is a comprehensive document that defines all the projects within the programme, detailing their scope, objectives, interdependencies, and delivery approach.
The MSP Practitioner states: “Only project dossier is created in defining programme from available options,” emphasizing that managing transition, producing the Programme Brief, and aligning projects with benefits realization occur in later programme stages.
Developing a well-structured Projects Dossier is critical for effective programme planning, control, and coordination of project delivery to achieve overall programme benefits.
MSP-Practitioner PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"