Which TWO are objectives of the ‘plan progressive delivery’ process?

Which TWO are objectives of the ‘plan progressive delivery’ process?

A.

To ensure that the controls are put in place to ensure that benefits realization continues in BAU.

B.

To ensure that the risks to the programme have been captured in a risk register and prioritized.

C.

To ensure that the approach to acquiring and managing the resources is defined.

D.

To ensure that the pace of delivery can be supported by the operational areas.A. 1 and 2B. 2 and 3C. 3 and 4D. 1 and 4