A company uses Microsoft 365 to track progress 3nd issues for construction projects.

A company uses Microsoft 365 to track progress 3nd issues for construction projects.

Project tasks must be tracked within aMicrosoft-maintained unified interface that can be shared and updated across multiple users.

You need to recommend a solution for the company.

What should you recommend?

A.

Microsoft To Do

B.

Microsoft Outlook

C.

Microsoft Stream

D.

Microsoft Planner