When should the Commissioning Authority (CxA) be brought onto the project team?
A.
At the end of Design Development (DD)
B.
Early in the Schematic Design (SD) phase
C.
Once Construction Administration (CA) begins
D.
Early in the Post-Occupancy Evaluation (POE)
The Answer Is:
B
This question includes an explanation.
Explanation:
According to LEED v4, the commissioning authority (CxA) should be contracted before the end of the Design Development (DD) phase and should be involved in the project team from early in the Schematic Design (SD) phase1.
References := LEED v4: Building Design + Construction Guide, LEED v4 -U.S. Green Building Council, SBGD - Part D – ConsultantScopes of Work 3. Commissioning Authority, What’s new in LEED V4 – Commissioning Changes - Steven Winter …, LEED ENHANCED COMMISSIONING | Steps and Downloads
LEED-Green-Associate PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"