A project has 16 employees working for four hours per day, 20 employees working six...

A project has 16 employees working for four hours per day, 20 employees working six hours per day, and 10 employees working eight hours per day. What is the Full Time Equivalent (FTE) occupancy of the project?

A.

28

B.

33

C.

33

D.

46