Which of the following is a prerequisite in LEED v4 Water Efficiency category?
A.
Rainwater Management
B.
Cooling Tower Water Use
C.
Building-Level Water Metering
D.
Building-Level Energy Metering
The Answer Is:
C
This question includes an explanation.
Explanation:
Building-Level Water Metering is a prerequisite in LEED v4 Water Efficiency category. Building-Level Water Metering means that the project must install permanent water meters that measure the total potable water use for the building and associated grounds. The project must also commit to sharing the water usage data with USGBC for at least five years after occupancy or certification. The LEEDGreen Associate Candidate Handbook states that this is one of the two prerequisites in the Water Efficiency category [1, p. 14]. References: [LEED Green Associate Candidate Handbook] , [Building-Level Water Metering | U.S. Green Building Council]
LEED-Green-Associate PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"