After the HVAC contractor has completed the rough-in installation of all air handling equipment, what...

After the HVAC contractor has completed the rough-in installation of all air handling equipment, what step should be taken to achieve Indoor Environmental Quality Credit, Contaminant Control during construction?

A.

Flush the building for 48 hours

B.

Open all the windows in the house

C.

Seal off all duct boots and vents

D.

Install temporary fans throughout the house