Which of the following Materials and Resources credits or prerequisites is reviewed under the design...

Which of the following Materials and Resources credits or prerequisites is reviewed under the design phase documentation submission?

A.

PBT Source Reduction - Lead, Cadmium, and Copper

B.

PBT Source Reduction - Mercury

C.

Building Product Disclosure and Optimization - Environmental Product Declarations

D.

Building Product Disclosure and Optimization - Sourcing of Raw Materials