During the early stages of a LEED project, the team was able to reduce the...

During the early stages of a LEED project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected a paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?

A.

IPc1: Integrative Design Process

B.

PRc1: Project Priorities

C.

EQc2: Occupant Experience

D.

MRc5: Construction and Demolition Waste Diversion