During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the...

During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractor substituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

A.

Energy meter location

B.

Equipment Maintenance Plan

C.

Owner ' s Project Requirements

D.

Coordination of other contractors