Which of the following criteria must a Commissioning Authority (CxA) comply with in order to meet the requirements of the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification of Building Energy Systems?

A.

Document commissioning authority experience for at least one building project

B.

Review the owner's project requirements (OPR) for project goals and expectations

C.

Be a part of the project's design and construction management team

D.

Report results, findings, and recommendations directly to the architect