A design team pursuing LEED for a new office building project calculated that with the...

A design team pursuing LEED for a new office building project calculated that with the water fixtures specified for the project, a 24% water reduction can be achieved compared to the LEED baseline. What does this mean to the team in terms of pursuing LEED?

A.

The project cannot pursue LEED

B.

The project may pursue Water Efficiency Credit, Indoor Water Use Reduction

C.

The project does not meet Water Efficiency Prerequisite, Indoor Water Use Reduction, but can make up the points elsewhere in the rating system

D.

The project can meet the Water Efficiency Prerequisite, Indoor Water Use Reduction, but cannot earn any points under Water Efficiency Credit, Indoor Water Use Reduction

LEED-AP-BD+C PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now LEED-AP-BD+C pdf
Get 70% Discount on All Products, Use Coupon: "coponace"