DEF, Inc.

DEF, Inc. is finalizing a contract to have its head office refurbished. Within its budget of $1.2 million there is a general risk fund of $30,000. The building is old, and the electrical wiring drawings do not appear up to date. The total project bid from Supplier X is $1 million. This includes a fee of $20,000 for updating electrical wiring drawings and the contractors' risk fund of $100,000, half of which is for building-related issues, and half of which is for electrical issues.

DEF decides to assume the risk of electrical issues. What is the contract price paid to Supplier X?

A.

5950,000

B.

$900,000

C.

51,000,000

D.

$930,000