it provides an optimal model for how the project should run
C.
it ensures sign-off of the Project Initiation Document
D.
it provides a framework of KPIs
The Answer Is:
B
This question includes an explanation.
Explanation:
Abaselinecaptures the originalscope–time–costmodel—the“optimal” start pointfor how the project should run. It is later used to compare actual performance and assess variance; it is not primarily a blame tool nor a sign-off mechanism.
[Reference:CIPS L5M8 Study Guide, p.228., ]