TheCritical Path Method (CPM)can provide a schedule for a project and demonstrates the longest path...

TheCritical Path Method (CPM)can provide a schedule for a project and demonstrates the longest path of activities to be completed. The critical path provides the longest “path” in terms of what?

A.

the largest number of steps that need to be completed

B.

the highest number of activities that need to be completed

C.

the longest time all activities will take to complete

D.

the most complex route to complete the activities