Which of the following is arisk in the supply chainwhich could affect the delivery of a project?
A.
project exceeds budget
B.
late delivery of items leading to delays
C.
vital project team members leave the organisation
D.
project scope increase
The Answer Is:
B
This question includes an explanation.
Explanation:
Alate deliveryby suppliers can directlydelay project timelines, representing asupply chain risk. The other options are internal project management risks, not supply chain-based.
[Reference:CIPS L5M8 Study Guide, p.205., ]