Which of the following is the correct order of the Deming Cycle?
A.
Plan, do, act, check
B.
Check, plan, do, act
C.
Plan, do, check, act
D.
Act, plan, check, do
The Answer Is:
C
This question includes an explanation.
Explanation:
The Deming Cycle (also known as the PDCA cycle) is a continuous improvement model. The correct sequence is: Plan, Do, Check, Act. According to the L5M5 study guide (p.276), it is used within ISO14001 and other management systems to improve processes iteratively. "Plan" involves identifying improvements, "Do" implements them, "Check" monitors results, and "Act" standardises successful changes. Procurement professionals apply this cycle in supplier management and sustainability programmes to ensure continuous improvement.
???? Reference: Managing Ethical Procurement and Supply (L5M5) Study Guide, p.276
L5M5 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"