In which part of the relationship cycle is a supplier likely to beleast motivated?
A.
Negotiation
B.
Signing the contract
C.
Handover from previous supplier
D.
Mid-term contract
The Answer Is:
D
This question includes an explanation.
Explanation:
Supplier motivation typicallydeclines mid-contract, once initial enthusiasm fades and before renewal discussions begin. Motivation peaks during negotiation, contract signing, and early delivery when relationships are still being established.