CIPS L4M6 Question Answer
In which procurement process is a PQQ not issued?
Open
Restricted
Competitive Procedure with Negotiation
Competitive Dialogue
Explanation
Open Tender processes are a one-stage process which issues and ITT. It has no PQQ (selection) stage. P. 77