CIPS L4M6 Question Answer
A procurement manager has established a project steering committee to undertake regular reviews and audits, and to ensure a successful buyer/supplier long-term partnership. The committee membership will comprise the procurement manager (chairperson), three of their cross-functional colleagues, the supplier's partnership project manager, and an independent member. Which of the following is a potential disadvantage of the proposed committee structure?