CIPS L4M6 Question Answer
A hospital awarded a contract to an IT consultancy to build and maintain their payroll and patient information systems. After a successful implementation, problems started to appear, with poor maintenance and accuracy of information, and slow response times from the supplier. After repeated problems, the decision to terminate the contract was agreed. Which of the following would be the priority legal concern for the hospital?