When might a company send a Request for Information (RFI) instead of a Request for...

When might a company send a Request for Information (RFI) instead of a Request for Quotation (RFQ)? (Select TWO)

A.

To obtain indicative prices that could be offered for a range of required products

B.

To negotiate the payment terms detailed in the terms and conditions of sale

C.

To ask for details of the product or range of services that the supplier has to offer

D.

To establish the details of environmental and quality certificates that the supplier may have

E.

To determine whether the supplier can fulfil a purchase order already placed