Blakenall District Hospital (BDH) is a large hospital that is a major part of the...

Blakenall District Hospital (BDH) is a large hospital that is a major part of the government’s health service. Purchasing staff are in the habit of placing many long-term contracts with suppliers and sub-contractors. Whilst these contracts are usually carried out successfully, prices are often paid that are well over budget. The purchasing manager is concerned to find that, in some cases, members of staff are forcing suppliers to accept fixed price contracts. The policy hascaused several problems such as some suppliers refusing to deal with BDH and a few going out of business mid-way through performing a contract with BDH. This is due to fluctuating market prices of materials. The procurement manager suggests supplier to adopt variable pricing arrangement with price index. Is this a right course of action?

A.

No, variable pricing would only benefit the suppliers

B.

Yes, this type of arrangement would provide absolute certainty when budgeting

C.

Yes, this pricing arrangement would reimburse the fluctuation of material prices

D.

No, price adjustment should be applied to short-term supply contract only (3-month duration or less)

L4M3 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now L4M3 pdf
Get 70% Discount on All Products, Use Coupon: "coponace"