The procurement officer for Hunter Manufacturing has been tasked to procure a new manufacturing software management system. They have consulted all relevant internal stakeholders and have the following high-level requirements: flexibility throughout the project, and the supplier to recommend the best solutions for building the system. Which type of specification should be developed?