A procurement team is categorising their purchased items into four quadrants of Kraljic's supply chain...

A procurement team is categorising their purchased items into four quadrants of Kraljic's supply chain portfolio matrix. They realise that there are some low-value items which come from very few suppliers in the market. The organisation is critically dependent on these suppliers. The team plans to reduce the dependence by finding alternative sources. Is this a right course of action?

A.

Yes, the organisation needs to reduce the supply risks

B.

No, the organisation should run competitive biddings to exploit the competition

C.

No, there is no way to escape this dependency

D.

Yes, this action will dramatically increase the supplier's bargaining power

L4M2 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now L4M2 pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"