How to approach this question:
- There are 4 sections to this essay, so before you start writing I’d make a couple of notes on each of the points. Then build those notes into separate paragraphs. Your notes may look like this:
How to manage the contract – ensuring contract is fit for purpose, holding XYZ to their responsibilities, ensuring ABC are also fulfilling their responsibilities, issuing contract variations if required, planning for contingencies.
- How to manage the supplier – ensure the right relationship is in place (transactional vs collaborative), communication – open and honest, ensure there is mutual trust and understanding of each other’s goals/ objectives.
- Ways of monitoring performance – use KPIs / SLAs, Supplier Scorecard, Vendor Rating, feedback from customers
- How to add value for ABC – increasing efficiencies (e.g. less product defects), improved quality, assisting with Value Engineering exercises, reduction in time and costs (e.g. through improved processes such as ordering), the supplier delivers ‘extras’ for ABC such as training to staff at no additional cost.
- Ensure each paragraph refers to Jan, ABC and XYZ. The question doesn’t state what the businesses are buying/ selling so you can use this as an opportunity to provide examples: ‘if ABC are procuring raw materials from XYZ such as metal, an effective way to manage performance would include …. If they are procuring a service, it may be more beneficial to use …. methodology’
Example Essay
Jan, the Contracts Manager at ABC Ltd, plays a pivotal role in ensuring the success of the recently awarded contract with XYZ Ltd. Efficient contract and supplier management involves careful planning, communication, performance monitoring, and the continuous addition of value. Here's how Jan can navigate these aspects:
In terms of contract management, Jan must ensure that the terms and conditions of the contract are "fit for purpose," aligning with the specific needs and complexity of the procurement. For instance, a simple goods procurement may necessitate a concise document, while more intricate projects like engineering endeavors may require a detailed contract such as a JCT or NEC contract. Additionally, Jan should vigilantly manage the contract during its lifespan, addressing any potential 'scope creep' that might necessitate amendments. If the contract lacks provisions for such changes, Jan may need to initiate the creation of a new contract to accommodate evolving needs
Clear delineation of responsibilities and contingencies is crucial in the contract to ensure accountability and preparedness for unforeseen circumstances. The inclusion of Key Performance Indicators (KPIs) and damage clauses, where appropriate, adds a layer of clarity and accountability to the contractual relationship. Planning for contingencies involves having backup strategies in place, especially considering potential challenges that may arise during the collaboration with XYZ Ltd. For example, having other suppliers she can call upon if XYZ fail to deliver on an order.
Turning to supplier management, Jan's role involves fostering a positive and productive relationship with XYZ Ltd. This includes regular meetings to discuss progress, achievements, and future plans. A mobilization meeting is particularly important to ensure a strong start to the contract. Subsequent monthly or quarterly meetings provide a platform to review performance retrospectively and plan for the future. Additionally, effective communication is paramount, with Jan ensuring that both organizations regularly communicate, particularly regarding urgent issues that may require immediate attention. This proactive communication can occur through various channels, such as email or phone calls, facilitating a swift resolution of any emerging concerns.
Trust and honesty form the bedrock of the relationship between ABC Ltd and XYZ Ltd. Jan should work towards fostering mutual trust through both formal and informal activities, recognizing the importance of a transparent and cooperative partnership
In terms of performance monitoring, Jan can employ Key Performance Indicators (KPIs) and Service Level Agreements (SLAs) to track performance regularly. These metrics should not be viewed as one-off activities but rather as ongoing tools for assessing and ensuring that performance aligns with expectations. Clear communication regarding the consequences of failing to meet these targets, such as the implementation of a Performance Improvement Plan or potential contract cancellation, is essential for maintaining accountability. Regular performance meetings between ABC Ltd and XYZ Ltd provide an opportunity to discuss achievements, setbacks, and any necessary adjustments. Beyond quantitative metrics, surveys and feedback from customers can provide qualitative insights into performance.
Finally, Jan can contribute to the partnership's success by focusing on adding value. This involves going above and beyond the contractual obligations, such as delivering products more efficiently at no additional cost or improving operational efficiencies. Encouraging XYZ Ltd to participate in Value Engineering exercises and engaging in Early Supplier Involvement to shape and define future requirements would be a good example of this. Additionally, providing 'add-ons' or 'extras' outside the contractual framework, such as training for ABC Ltd staff, further enhances the value derived from the partnership.
In conclusion, Jan's role as Contracts Manager extends beyond the initial awarding of a contract- rather her role involves strategic contract and supplier management throughout the lifetime of the professional relationship. By ensuring the contract is well-suited for its purpose, fostering a positive relationship with the supplier, monitoring performance effectively, and consistently adding value, Jan contributes to the success of the collaboration between ABC Ltd and XYZ Ltd. This comprehensive approach sets the stage for a mutually beneficial and enduring partnership.
Tutor Notes:
- A case study question like this in the real exam is likely to come with more details. They often come with lots and lots of details to be honest, talking about what XYZ supplies to ABC and the names of the people involved. The case study usually gives you some good clues as to what the examiner will be looking for you to include, so do read them carefully.
- You don’t have to include much ‘theory’ on case study questions – the important thing is to reference Jan as much as possible. BUT you could throw in a cheeky mention of the Kraljic matrix. The approach to managing the contract and supplier would depend on the type of item supplied by XYZ – e.g. if it is a bottleneck item the supplier may need to be handled differently to if it is a routine item. You could also mention KPIs and objectives as being ‘SMART’ - Specific, Measurable, Attainable, Relevant, and Time-Bound
- study guide p.86-90 / p.94 / p.96 -98