When is a shunt trip operated to power down an elevator?
A.
When a heat detector is tripped
B.
When a pull station is activated
C.
When a smoke detector is tripped
D.
When a sprinkler head is activated
The Answer Is:
D
This question includes an explanation.
Explanation:
Elevators must beshut downwhen there iswater dischargein the hoistway to prevent electrical hazards and damage. This shutdown is done using ashunt trip breaker.
NFPA 72 (2022), Section 21.4.2:
“Where sprinklers are located in the elevator machine room, control space, or hoistway, means shall be provided to automatically disconnect the main power supply to the elevator prior to the application of water.”
This is triggeredby a waterflow switch or heat detector, but the standard design uses thesprinkler head activationas the point of shutdown via heat detector.
Important: While the heat detector usually triggers the shunt trip, thesprinkler head activationis the condition being detected.
Correct answer: D. When a sprinkler head is activated
===========
ITFAS-Level-1 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"