An enterprise is currently experiencing an unacceptable 8% processing error rate and desires to manage...

An enterprise is currently experiencing an unacceptable 8% processing error rate and desires to manage risk by establishing a policy that error rates cannot exceed 5%. In addition, management wants to be alerted when error rates meet or exceed 4%. The enterprise should set a key performance indicator (KPI) metric at which of the following levels?

A.

5%

B.

4%

C.

8%