During which main group of test activity are the following tasks performed?

During which main group of test activity are the following tasks performed?

•Checking test results and logs against specified coverage criteria.

•Assessing the level of component or system quality based on test results and logs.

•Determining whether more tests are needed.

Select the correct answer:

A.

Test planning.

B.

Test analysis.

C.

Test design.

D.

Test monitoring and control.