During iteration planning, a scrum team uses an estimation technique called planning poker to estimate...

During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the team agreed on some ground rules to limit the number of poker rounds and save time.

The team agreed on the following:

1. They will use the following progression for estimation: Extra-small, Small, Medium, Large, Extra-large, and Extra-extra-large.

2. If estimation values differ significantly, the highest score will be used for estimation purposes.

The result of the first round of planning poker:

Team MemberEstimation

BusinessLarge

DevelopmentExtra-extra-large

TestingExtra-extra-large

Which of the following options best represent the team’s next actions?

A.

The fact that all estimations are high indicate that the user story is not well understood or should be broken down into multiple smaller stories.

B.

The pre-agreed rules state that the highest score should be used for estimation, resulting in the user story being categorised as Extra-extra-large.

C.

Since the business representative is likely to have the most informed view of the requirement, the user story is categorised as a Large.

D.

the team discusses the differences in the estimates and repeats the poker round until an agreemet is reached.

ISTQB-CTFL PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now ISTQB-CTFL pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"