PECB ISO-IEC-42001-Lead-Auditor Question Answer
After an AIMS audit, the auditee made the required corrections and implemented corrective actions. However, it did not notify the auditor that led the audit regarding the completion status of the corrections and corrective actions since the auditee had been recommended for certification under the condition that corrective actions be submitted without a prior visit. Is this acceptable?