Your project sponsor has requested a cost estimate for the project on which you're working.

Your project sponsor has requested a cost estimate for the project on which you're working. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide to use ___________________.

A.

parametric modeling techniques

B.

analogous estimating techniques

C.

bottom-up estimating techniques

D.

computerized modeling techniques