BCS ISEB-PM1 Question Answer
You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the project scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the project scope statement. This deliverable is a critical success factor.
Which of the following actions should you take?