The project budget is set at $150,000.

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:

Actual cost = $50,000 Plan cost = $45,000 Earned value = $40,000

What is the cost performance index?

A.

0.80

B.

0.89

C.

1.13

D.

1.25