The decision to approve or reject a particular change request is made in which of...

The decision to approve or reject a particular change request is made in which of the following processes?

A.

Perform Integrated Change Control

B.

Monitor and Control Project Work

C.

Develop Project Management Plan

D.

Direct and Manage Project Execution